# What a local data center means for residents

By J. Rin, USAF Veteran.  Executive Editor of Record.  Published 10 November 2026.  Updated 10 November 2026.

Canonical: https://datacenterskilledtrades.com/guides/what-a-local-data-center-means-for-residents/

A data center can bring a county large property tax payments and a big, short construction workforce, but few permanent jobs.  It can also add grid costs that other utility customers help pay, use a little or a lot of water depending on its cooling design, and bring constant low-frequency noise when it sits near homes.  Virginia's legislative audit agency (JLARC) found in December 2024 that most economic benefits come during construction, that a typical 250,000-square-foot data center may have about 50 full-time workers, and that a typical Dominion Energy residential customer could see generation and transmission costs rise an estimated $14 to $37 a month in real dollars by 2040.  What a community actually gets depends on local tax rates, zoning, state incentives, and any signed agreement.  Florida enacted a law in 2026 that requires utility tariffs to make customers of 50 megawatts or more bear their own full cost of service, and the Florida Public Service Commission is now reviewing utility filings under it.

This page states only what named primary sources document, with dates and status.  It does not treat a planned project as built, and it does not claim that a project creates demand or jobs unless the cited source says so.

Related briefs on this site: [grid load](https://datacenterskilledtrades.com/briefs/grid-load/), [water](https://datacenterskilledtrades.com/briefs/water/), [noise](https://datacenterskilledtrades.com/briefs/noise/), and [jobs outlook](https://datacenterskilledtrades.com/briefs/jobs-outlook/).  Trade and leadership paths are on the [roles](https://datacenterskilledtrades.com/roles/) and [management](https://datacenterskilledtrades.com/management/) hubs.  A local-government question list is at [questions for local government](https://datacenterskilledtrades.com/briefs/local-gov-questions/).

JRBy J. Rin, USAF Veteran.  Executive Editor of Record.  Published 10 November 2026.  Updated 10 November 2026.

## How to read this page

Where a figure is a budget projection or a model forecast, it is labeled that way.  Past events are written in the past tense.  National statistics are national.  A Loudoun County, Virginia, document describes Loudoun County, not every community.  If a source does not give a local headcount, gallon total, or job figure, this page does not invent one.

**Method.**  Sources are statutes, regulatory orders and filings, county and state agency documents, signed agreements, and national laboratory and federal statistical reports.  Every figure and quotation on this page was checked against its source document on 10 November 2026.  Quotations are exact.  Industry estimates, projections, and contract commitments are labeled as such.  Benefits and costs are reported from the same kinds of sources with the same level of detail.

**Scope.**  This page is nonpartisan.  It does not recommend for or against any project, policy, or candidate, and it does not characterize any official or party.  It reports what the cited documents say.

**Last reviewed:** 10 November 2026.  **Corrections:** email [welcome@datacenterskilledtrades.com](mailto:welcome@datacenterskilledtrades.com) with the passage and the source.  See [how to cite this page](https://datacenterskilledtrades.com/guides/what-a-local-data-center-means-for-residents/#cite).

## Key numbers, with sources

Each figure keeps the scope its source gave it.  Virginia figures describe Virginia.  Projections and estimates are labeled.

| Figure | What it measures | Source and date |
|---|---|---|
| 31% and 7% | Data center share of total local tax revenue in Loudoun and Prince William counties, Virginia | JLARC, Data Centers in Virginia, Report 598, 9 December 2024 |
| Under 1% to 31% | Range of data center revenue as a share of total local revenue across five Virginia localities with mature markets | JLARC, December 2024 |
| $104.4 million | Loudoun County property tax revenue increase, FY 2025 over FY 2024 (all property, not only data centers) | Loudoun County PAFR, FY ended 30 June 2025 |
| $1.3 billion (40%) | Projected data center revenue in Loudoun's adopted FY 2027 budget (a projection, not an actual) | Loudoun Data Center Fact Sheet, as of 1 March 2026 |
| $327.5 million | Estimated ad valorem tax revenue for local taxing jurisdictions over 20 years from planned Project Helium, Barber County, Kansas, with no abatement (county estimate) | Barber County Commissioners, 31 August 2026 |
| About 50 | Full-time workers at a typical 250,000-square-foot data center, about half of them contract workers (industry estimate) | JLARC, December 2024 |
| Over 8,000 | Full-time data center jobs in Virginia in FY 2023, direct employees and contract workers combined (JLARC staff estimate) | JLARC, December 2024 |
| About 1,500 | Workers on site at the height of construction of one building, which usually takes 12 to 18 months (industry estimate) | JLARC, December 2024 |
| 74,000 jobs | Estimated annual statewide contribution of the industry, with $5.5 billion in labor income and $9.1 billion in GDP, mostly from construction (model estimate) | JLARC, December 2024 |
| $928.6 million | Sales tax data centers and tenants reported saving in FY 2023 under Virginia's exemption (state, local, and regional portions), of which about $683 million was the state portion | JLARC, December 2024 |
| $14 to $37 a month | Estimated rise in generation and transmission costs for a typical Dominion residential customer by 2040, in real dollars (projection) | JLARC, December 2024 |
| $11.24 a month | Approved 2026 base-rate increase for a typical Dominion residential customer, with $2.36 more in 2027 (all causes, not only data centers) | Virginia SCC, 25 November 2025 |
| 50 MW | Florida threshold for a "large load customer," whose utility tariff must reasonably ensure it bears its own full cost of service | Florida Statutes s. 366.043, Ch. 2026-65, effective 1 July 2026 |
| 100 MW and $150 million | Minimum critical IT load and cumulative capital investment for Florida's data center sales tax exemption | Florida Statutes s. 212.08(5)(r) |
| 6.7 million gallons | Yearly water use of an average large office building.  JLARC found most data centers use about that much or less, while 11 buildings each used over 50 million gallons in 2023 | JLARC, December 2024 |
| 2.1 billion gallons | Virginia data center water use in 2023, just over a third of it reclaimed water, under 0.5% of state withdrawals | JLARC, December 2024 |
| 192 TWh (4.7%) | Estimated U.S. data center electricity use in 2024 and its share of national consumption | LBNL, 2025 Update, June 2026 |
| 20% to 30% | Share of land development in Loudoun and Prince William counties from 2013 to 2021 that came from data centers (estimate) | JLARC, December 2024 |
| One-third | Share of Virginia data centers located near residential areas.  At least 15, about 10% of operating sites, appear to have generated noise nearby residents regard as problematic | JLARC, December 2024 |

## Tax revenue

Loudoun County's Popular Annual Financial Report for the fiscal year ended 30 June 2025 is the county's short-form financial report to residents.  The report itself states that it is not a substitute for the audited Annual Comprehensive Financial Report, that it does not conform to Generally Accepted Accounting Principles, and that its figures are extracted from the audited ACFR.

The PAFR states that fiscal year 2025 was "another year of revenue and tax base growth, with a property tax revenue increase of approximately $104.4 million from FY 2024."  Property tax, the report says, includes real property and personal property.  The increase "was a result of growth in assessment values."  The "main factors driving the increase in revenues," the report says, were "the growth in the new construction of commercial properties, increase in assessed values of commercial properties, personal property taxes on computer equipment and vehicles."

On General Fund results, the PAFR states that for FY 2025, actual tax revenues from all sources, including local, commonwealth, and federal, exceeded amended budget amounts by $154.9 million.  Real property taxes "provided $9.7 million of the increase."  "Personal property taxes for computer equipment in data centers exceeded the budget by $29.6 million."  Other personal property increases, "including vehicles, accounted for $39.0 million of the increase."  The PAFR also states that 79 percent of General Fund revenues and other financing sources came from property taxes on real and personal property.

The same report states that in April 2025 the Board set the calendar year 2025 real property tax rate at $0.805 per $100 of assessed value, "$0.060 lower than the previous rate of $0.865 for the calendar year 2024."  It attributes the rate decrease to an increase in real property values, "while still providing sufficient revenue to support Loudoun County government and Loudoun County Public Schools."  It also notes that in April 2025 the county adopted a budget for FY 2026 that "totaled approximately $4.7 billion in total appropriations for the general county government and public school system."

A separate Loudoun County Data Center Fact Sheet, dated as of 1 March 2026, describes both sides of the ledger in the county's own words: "The rapid development of the data center industry in Loudoun County has resulted in economic benefits and concerns among residents about the impact of data centers on the surrounding community."  Under 2026, the fact sheet states: "The FY 2027 adopted budget projects data center revenue at $1.3 billion, representing 40% of the total budget."  That $1.3 billion figure is a projection in the adopted FY 2027 budget, as the fact sheet itself says, not an audited FY 2025 actual.

The fact sheet's tenth "lesson learned" is about how to use that money: "Use data center revenue strategically to support capital improvement projects and one-time expenditures, rather than ongoing or recurring expenses, to avoid becoming reliant on a revenue stream that may change over time."  That is Loudoun County's stated guidance, not a forecast of future collections in another locality.

## Tax incentives and what they cost

Property tax is only one side of the ledger.  States and counties often give data centers tax breaks, and those breaks are a cost to the public, paid as revenue the government does not collect.

**Virginia.**  JLARC reported that Virginia has offered a retail sales and use tax exemption to large data centers since 2010.  It lets data centers and their tenants buy servers, network gear, cooling equipment, and generators without paying sales tax.  To qualify, a data center must create at least 50 jobs paying at least 150 percent of the prevailing annual average wage in its locality and make a $150 million capital investment, with lower thresholds in distressed areas.  Data centers and tenants reported saving $928.6 million in sales taxes in FY 2023, counting the state, local, and regional portions of the tax.  JLARC estimated the state portion at $683 million, "making it by far the state's largest economic development incentive, with the next closest incentive valued at $74 million."  About 90 percent of the industry, measured by megawatts, used the exemption.  At the time of the report, the exemption was scheduled to expire in 2035, and JLARC laid out options for the General Assembly to extend it, let it lapse, or make it partial.

JLARC also noted a local trade-off: some localities "have greatly reduced their business personal property tax rates for computer equipment to try to attract data centers, but this also reduces the revenue they can collect from the industry."

**Illinois.**  The Illinois Department of Commerce and Economic Opportunity (DCEO) runs a Data Center Investment Program that, as its program page describes it, provides qualifying data centers exemptions from a variety of state and local taxes, plus a tax credit of 20 percent of wages paid to construction workers for projects in underserved areas.  DCEO's program page lists the eligibility rules: the data center and its tenants must collectively make a capital investment of at least $250 million over 60 months, create at least 20 new full-time or full-time equivalent jobs with total compensation of at least 120 percent of the county median wage, and be carbon neutral or certified under a green building standard.  The exemptions have a 20-year life.  On 5 June 2026, the Governor of Illinois directed DCEO to pause processing agreements for the program starting 1 July 2026, and DCEO's page states it will no longer process applications as of that date.  The Governor's release said pausing state incentives was needed "to understand whether these incentives are driving development that is insensitive to consumer costs and environmental impact," and that existing agreements, including those entered into before 1 July 2026, will be honored.

**A county that gave no abatement.**  In Barber County, Kansas, the county commission announced on 31 August 2026 that it had signed agreements with Google for a planned data center called Project Helium.  The county said Google "will pay 100% of ad valorem property taxes, with no property tax abatement."  The county estimated about $327.5 million in total property tax revenue for local taxing jurisdictions over 20 years, about $138.4 million of it for the county.  For scale, the county reported its whole current assessed valuation as $115,465,673 and its total 2026 property tax as $6,768,132, against a projected assessed value for the project of $116,875,000.  The county also projected $1 million to $1.5 million a year in sales tax on Google's electricity purchases.  Those are county estimates for a project that had not been built when the release was issued.

**Florida.**  Florida exempts qualifying data center property from sales tax.  See the [Florida section](https://datacenterskilledtrades.com/guides/what-a-local-data-center-means-for-residents/#florida) below for the terms.

## Water use

The fact sheet lists water as one of its top considerations.  It states: "Local water systems are cyclical and managed with precision.  Any new data center connecting to municipal water supplies or wastewater systems should be evaluated for its potential impact on the overall water cycle, in both the near- and long-term."  The document does not publish a Loudoun County gallon total for data centers on the pages extracted for this article, so this page does not invent one.

National direct-use figures come from Lawrence Berkeley National Laboratory's *2024 United States Data Center Energy Usage Report* (Shehabi, Smith, Hubbard, and coauthors, December 2024).  That report estimates that in 2014, data centers "consumed 21.2 billion liters of water, with 64% in internal data centers."  "By 2023, hyperscale and colocation account for 84% of the 66-billion-liter total, while internal data centers fell to just 12%."  The report then gives a forward range: "Hyperscale data centers in 2028 are expected to consume between 60 and 124 billion liters."  That 2028 range is a projection.

The same 2024 report also estimates indirect water, meaning water consumed at power plants that supply the electricity.  It states that U.S. data centers consumed approximately 176 TWh in 2023, and that "the total indirect water footprint of U.S. data centers is nearly 800 billion liters" for that electricity, based on the regional grid mix at data center locations.  It reports a national average of 4.52 liters per kWh of indirect water consumption in 2023.  Those are modeled national totals, not a measurement of a single county system.

Virginia has measured numbers.  Using water utility data, JLARC found that most data centers "use about the same amount of water (or less) as an average large office building (6.7 million gallons per year), although a few require substantially more, and some require less than a typical household."  In 2023, 11 data center buildings each used over 50 million gallons, including one that used 243 million gallons, which was 10 percent of the industry's total.  Statewide, data centers used an estimated 2.1 billion gallons in 2023, with just over a third coming from reclaimed water, and accounted for less than 0.5 percent of total state withdrawals.  JLARC said water is more limited for localities without large surface water supplies or inside groundwater management areas, and it recommended that the General Assembly expressly let local governments require water use estimates for proposed data centers.

Cooling design matters.  The planned Project Jupiter campus in Doña Ana County, New Mexico, committed in its community benefits agreement to a closed-loop cooling system with average potable water use of 20,000 gallons per day at full buildout, capped at a 60,000-gallon daily peak.  Barber County, Kansas, said its planned Project Helium will be "a closed-loop, air-cooled facility, not a water-cooled facility," and that Google will not drill new water wells on the property.  Those are commitments for projects that were not operating when the documents were issued, not measured use.

## Power use

LBNL's later *United States Data Center Energy Usage Report: 2025 Update* (Smith, Hubbard, Newkirk, Ganeshalingam, Holecek, Sartor, Mills, and Shehabi, June 2026, LBNL-2001758) revises the electricity estimates.  It states: "The updated estimate of data center electricity use in 2024 is 192 terawatt-hours (TWh), accounting for 4.7% of total U.S. electricity consumption."  The 176 TWh figure in the December 2024 report was that report's estimate for 2023.  The two numbers are not interchangeable.

The 2025 Update also publishes forecasts, which this page labels as such.  Its Reference Case forecast for 2030 is 649 TWh, "representing 11.8% of forecasted 2030 U.S. electricity use as presented in the 2025 North American Electric Reliability Corporation (NERC)" long-term reliability assessment, as cited in the report.  The report's compounded uncertainty range is 521 to 843 TWh, equal to 9.5% to 15.3% of total U.S. electricity use in 2030.  Those 2030 figures are model results, not measured 2024 use.

The U.S. Energy Information Administration, in a 19 May 2026 Today in Energy analysis by Courtney Sourmehi, reported Annual Energy Outlook 2026 projections for electricity consumed by data center servers.  EIA wrote that, by 2050, server consumption alone reaches between 446 billion and 818 billion kilowatthours, with the high end from the High Electricity Demand case.  "Across all cases, servers alone accounted for an estimated 7% of commercial sector electricity consumption in 2025."  EIA also projected that data center server electricity use grows to 22% to 33% of commercial building electricity use by 2050 across its cases.  Those 2050 shares are projections from AEO2026.

## Grid and rate cases

Higher load on a utility system can show up in rate cases, transmission plans, and wholesale markets.  Who pays is a regulatory question, not a fact that can be read off a national TWh total.  The sources below document one completed Virginia case and a national short-term outlook.  Florida's 2026 law and its pending tariff reviews are in the [Florida section](https://datacenterskilledtrades.com/guides/what-a-local-data-center-means-for-residents/#florida).  None of these settle cost allocation in other states.

On 25 November 2025, the Virginia State Corporation Commission issued its final order in Case No. PUR-2025-00058, the 2025 biennial review of Virginia Electric and Power Company (Dominion Energy Virginia) rates, terms, and conditions.  In a news release that day, the Commission stated that it had rejected Dominion's requested base-rate increases of $822 million in 2026 and $345 million for 2027.  "Instead, it found that the evidence presented supports an increase of $565.7 million in 2026 and $209.9 million in 2027."  The release said that for a typical residential customer, "the approved rates would mean monthly increases of $11.24 in 2026" (23.7% lower than Dominion's request) "and $2.36 in 2027" (51.2% lower than requested).  The Commission also "approved an increase in Dominion's authorized return on equity from 9.7% to 9.8%, less than the company's requested return of 10.4%."

The final order itself finds those $565.7 million and $209.9 million annual base-rate revenue increases "just and reasonable."  It states that the adjustments "result in approximate monthly bill increases for a typical residential customer of $11.24, or 7.5%, in 2026 and an additional $2.36, or 1.5%, in 2027."  The order says the approved rates "shall take effect for service rendered on and after January 1, 2026, and January 1, 2027."

The same order directs the company to implement a new Rate Schedule GS-5, effective 1 January 2027.  The GS-5 class shall include customers with a measured or contracted demand of 25 megawatts or greater on a contiguous site, and a measured or expected load factor of at least 75%.  The Commission's 25 November 2025 news release described this as "a new rate class for the biggest users of electricity, including data centers," and said the class was approved "to help insulate ratepayers from the costs around the rapid build-out and construction of infrastructure to support businesses such as data centers."

The order approves minimum demand charges of 85% of contracted demand for distribution, 85% of contracted demand for transmission, and 60% of contracted demand for generation.  It also approves a 14-year contract term for customers taking initial service and signing an electric service agreement on or after 1 January 2027, with an exit fee covering outstanding minimum charges if the customer ceases operations or otherwise defaults during the term.  Collateral requirements in the order likewise apply to customers taking initial service and signing an ESA on or after that date.  The order exempts certain legacy customers: minimum demand charges "shall not apply to a customer that was taking service from the Company prior to January 1, 2016," with additional exemptions from the minimum generation demand charge for specified competitive-supply and interruptible-service situations as of 1 January 2025.

An SCC fact sheet posted 24 February 2026, titled "SCC Data Center Initiatives," summarizes those PUR-2025-00058 determinations as steps "designed to ensure that large load customers, such as hyperscale data centers, appropriately pay for the costs incurred to serve them."  The fact sheet also states that the Commission ordered Dominion to submit alternative cost allocation proposals in future proceedings, and to submit its process for interconnecting large-load customers for SCC review "on or before February 2, 2026."  This page does not treat that future-proceeding work as already decided.

National residential prices are a different series.  EIA's Short-Term Energy Outlook dated 6 October 2026 (forecast completed 1 October 2026) reported U.S. residential electricity prices of 16.5 cents per kilowatthour in 2024 and 17.3 cents in 2025, and projected 18.2 cents in 2026 and 18.7 cents in 2027.  The same outlook said wholesale prices "are just one component of residential electricity prices," which "include other expenses such as transmission and distribution upgrades, capacity market auction prices in some regions, among other expenses."  It forecast that "electricity demand from the commercial sector, which includes data centers, [is] to increase steadily throughout 2027, growing by 2.8% year-over-year."  The outlook attributed some regions' higher wholesale prices in 2026 "mainly due to weather events, such as winter storm Fern and high summer temperatures particularly in July."  This page does not reassign that weather language to data centers.

Loudoun County's fact sheet, writing about energy and electrical infrastructure, states that "Planning appropriately for the energy needs of data centers is as important as planning for the siting, design, and operation of the data centers themselves," and that if electrical infrastructure is not adequate, "new high-voltage transmission lines and towers, along with distribution substations, may need to be constructed."  That is a siting lesson, not a list of lines already built in a named corridor.

JLARC commissioned an independent study of Virginia utility cost recovery.  It found that data centers "are currently paying their full cost of service," but that "data centers' increased energy demand will likely increase system costs for all customers, including non-data center customers."  The reasons JLARC gave were new generation and transmission that would not otherwise be built, higher energy prices if supply cannot keep pace, and more exposure to market price spikes if utilities import more power.  It estimated that "a typical residential customer of Dominion Energy could experience generation- and transmission-related costs increasing by an estimated $14 to $37 monthly in constant (or real) dollars by 2040."  JLARC also flagged a stranded-cost risk: if forecast demand does not materialize, or several large data centers close, existing customers could be left paying for infrastructure.  It named a separate data center customer class as one way to protect other customers, and the SCC order described above created a large-load class in Dominion's 2025 review.

Some projects promise to supply their own power.  The Project Jupiter agreement says its onsite microgrid, with natural gas generation and battery storage, "will be paid for by the Companies" and "will not impact existing customers' power reliability or costs."  That is a contractual commitment for a planned campus, not a finding from a utility commission.

## Noise

Loudoun County's "Data Centers: Noise and Air Quality Concerns" page states that the eastern suburban and urban policy areas are "home to nearly 200 operational data centers," and that "the mingling of residential and data center development raises the profile of a number of community impacts, including noise concerns and air quality issues."

The county page states that data center campuses can include noise from "lighting, cooling, mechanical systems and the electricity needed to run them," as well as "HVAC units and emergency backup generators," and that campuses "may feature onsite energy generation and energy storage systems, which also produce noise."  It describes "a persistent hum or buzzing sound" in a narrow frequency range, "broadly known as tonal noise," and says "single frequency tones can be more aggravating to the human ear than broadband background noise at similar volumes."  It also states that facilities can generate low-frequency noise, and that "the scientific community acknowledges a need for more research to assess the long-term impacts of low-frequency noise."

Under the Loudoun County Zoning Ordinance, as described on that page, data centers "are required to submit a pre-construction noise study at the time of site plan review as well as a post-construction noise study submitted at least one month but no more than 12 months after the issuance of the first Certificate of Occupancy."  "For residential properties, the maximum allowable sound level at the property line is 55 dBA."  The county states that noise complaints "are among the most persistent issues brought forward to Loudoun County officials and frequently pertain to tonal noise."  It also states: "The county does not currently have policy or regulatory language specific to tonal noise or low frequency noise."  As part of the Data Center Standards and Locations project initiated by the Board of Supervisors in 2024, "the county is working to identify new policy and regulatory mechanisms to address data center noise, including tonal noise and low frequency noise."  "Amendments to the county's Comprehensive Plan and Zoning Ordinance are anticipated in spring or summer 2027."  That is an anticipated schedule, not an adopted 2027 ordinance.

The same Loudoun page notes a Virginia statute, now codified as Code of Virginia section 15.2-2209.5.  The code, titled "Siting of data centers; site assessment" and cited as 2026, cc. 567, 568, defines a "high energy use facility" as a facility that an applicant reasonably anticipates, at the time of a rezoning, special exception, or special use permit application, "will require 100 megawatts or more of electrical power from an electric utility providing retail service to the facility."  Before approving such an application for a new high energy use facility, a locality "shall require that an applicant perform and submit a site assessment to examine, to the extent practicable," "the sound profile of the HEUF on residential units and schools located within 500 feet of the HEUF property boundary."  A locality may also require the assessment to examine effects on ground and surface water, agricultural resources, parks, registered historic sites, and forestland.  The electric utility is to submit a form describing substations and anticipated transmission voltage, to the extent known and practicable.  The section "shall not apply to a site with an existing legislative or administrative approval where an applicant is seeking an expansion or modification of an already existing or approved facility and such expansion does not exceed an additional 100 megawatts or more of electrical power."

On air quality, the Loudoun page states that "the majority of data centers in Loudoun County run their backup diesel generators for one hour, once per week, for mandatory testing," and "may turn to backup power on the rare occasion there is an interruption to their power supply from the grid or if ordered to do so by the regional transmission organization, PJM, due to extreme electrical demand on the grid."  It states that "there is only one data center in Loudoun that is reliant on off-grid power full time, and that facility runs on natural gas turbines."  The page also states that Loudoun County "does not have the authority to regulate exterior air quality conditions; that falls under the purview of the Virginia Department of Environmental Quality (DEQ)," and that, as described by the county, "On July 1, 2026, DEQ began mandating Tier 4-equivalent emissions standards for new or modified generators at data center sites."

## Land use and zoning

JLARC counted about 150 data center sites in Virginia holding around 340 buildings, with over 63 million square feet of data center space on 7,200 acres.  It estimated that data centers accounted for 20 to 30 percent of land development in Loudoun and Prince William counties from 2013 to 2021, and that data center development had grown another 50 percent since then.  JLARC added a caution in the other direction: these are fast-growing counties, so "some portion of land developed for data centers likely would have been developed for other uses, such as housing, mixed-use commercial space, or distribution centers."

On neighbors, JLARC found that "the industrial scale of data centers makes them largely incompatible with residential uses" and that one-third of Virginia data centers are near residential areas.  It traced that to local decisions: zoning ordinances that did not treat data centers as an industrial use, industrial zones drawn next to neighborhoods, and rezonings that elected officials approved next to sensitive locations.  JLARC also found that "the majority of data centers are appropriately located in industrial or commercial areas," that over 60 percent are more than 500 feet from residentially zoned property, and that "a minority of data centers have generated noise complaints."  At least 15 data centers, about 10 percent of operating sites, appeared to have generated noise that nearby residents regard as problematic.  Almost one-third, 29 percent, of operating data center properties were within 200 feet of residentially zoned property.

Loudoun County's fact sheet adds a land-value caution among its top 10 lessons: "Be mindful of the potential for data centers to make land unaffordable to other commercial or residential developers."

Power for a campus can also take land.  JLARC estimated that new utility-scale solar alone could require 73,000 to 165,000 additional acres in Virginia by 2040, depending on the demand scenario.  That is a statewide planning estimate, not a measure of any one project.

## Jobs and construction

Official employment statistics do not publish a count of "data center jobs" in a given county.  The measurable national industry payroll series that is closest in official statistics is the Bureau of Labor Statistics Current Employment Statistics series CES5051800001, titled "All employees, thousands, computing infrastructure providers, data processing, web hosting, and related services, seasonally adjusted" (NAICS 518, Information supersector).  That industry is broader than on-site data center operations.  It is not a local headcount, and it is not a count of electricians, HVAC technicians, or pipefitters.

As retrieved from the BLS series page on 10 November 2026, CES5051800001 stood at 480.9 thousand in December 2024, 472.9 thousand in December 2025, and a preliminary 454.8 thousand in both September 2026 and October 2026.  Those are national, seasonally adjusted totals in thousands of employees.  This page does not treat a decline or an increase in that series as proof that a named local project created or eliminated jobs.

Construction employment sits in other CES series that also are not data-center-specific.  Series CES2000000001, "All employees, thousands, construction, seasonally adjusted" (NAICS 23), stood at 8,276 thousand in December 2024, 8,272 thousand in December 2025, and a preliminary 8,367 thousand in October 2026.  Series CES2023800001, "All employees, thousands, specialty trade contractors, seasonally adjusted" (NAICS 238), stood at 5,239.2 thousand in December 2024, 5,222.4 thousand in December 2025, and a preliminary 5,281.0 thousand in October 2026.  Specialty trade contractors include electrical, HVAC, plumbing, and every other specialty across every building type.  Those national totals are not a campus construction headcount.

A data center that is still in site plan or legislative review is not an operating facility.  Loudoun County's fact sheet states that in 2025, in Phase 1 of its standards project, "the Board of Supervisors ends by-right development of most data centers, meaning that future proposed data centers must go through a legislative review process including public input," with "a grandfathering resolution" that "allows certain pending applications to continue through the by-right process."  In 2026, "Phase 2 of the project is underway."  Construction of a reviewed and permitted project, when it occurs, can include building work and, as the fact sheet notes, possible new transmission lines, towers, and substations if electrical infrastructure is not already adequate.  That is not a claim that any one proposed project has been built, or that it hired a stated number of workers.

**Construction versus permanent jobs.**  JLARC's numbers, drawn from data center representatives, show the gap plainly.  Building one data center usually takes 12 to 18 months, and "at the height of construction, approximately 1,500 workers are on site from various construction-related industries."  Once it runs, "a typical 250,000-square-foot data center may have approximately 50 full-time workers, about half of which are contract workers."  JLARC described those operating jobs as tending to be high paying.  By JLARC staff estimates, data center direct employees and contract workers held over 8,000 full-time jobs in Virginia in FY 2023, and data centers added more than 800 new full-time jobs that year.  Its statewide model estimate of 74,000 jobs, $5.5 billion in labor income, and $9.1 billion in GDP a year, based on average industry spending from FY 2021 to FY 2023, comes mostly from the construction phase rather than ongoing operations.  JLARC put those estimates at just over 1 percent of statewide employment, income, and GDP, and noted that the method does not account for the cost of some potential externalities, such as health and environmental costs tied to carbon emissions.

Signed agreements sometimes put job minimums in writing.  The Project Jupiter community benefits agreement, executed 12 November 2025, says the campus "expects to create at least 2,500 construction jobs onsite" during construction anticipated from 2025 to 2028, and commits to "a minimum of 750 new full-time equivalent jobs and 50 part-time jobs within three years of commencing operation," with an average annual wage between $75,000 and $100,000.  Barber County said its agreement requires Google to "guarantee a minimum of 300 full time equivalent jobs by the fifth year of project operations."  Both are planned projects, so these are commitments, not counts of people hired.

For tradespeople, the construction phase is where most of the hours are.  The trades that do that work, and what they earn, are covered on the [roles](https://datacenterskilledtrades.com/roles/) hub, the [power and cooling careers guide](https://datacenterskilledtrades.com/guides/power-and-cooling-careers/), and the [who gets hired brief](https://datacenterskilledtrades.com/briefs/who-gets-hired/).  Supervisors and project leads can start at the [management](https://datacenterskilledtrades.com/management/) hub.  On our sister site, [HighPayingTrades' state licensing checker](https://highpayingtrades.com/tools/state-licensing-checker/) shows what each state requires for electricians, plumbers, and HVAC techs, and its [time-to-$100K calculator](https://highpayingtrades.com/tools/time-to-100k/) estimates how long a trade path takes to reach that pay level.

For a fuller discussion of what official tables do and do not count, see the [jobs outlook brief](https://datacenterskilledtrades.com/briefs/jobs-outlook/).

## Florida: tax exemption, 2026 law, and utility tariffs

Three kinds of official records matter most for Florida residents: a state sales tax exemption for large data centers, a 2026 law on large-load customers and water permits, and utility tariffs reviewed by the Florida Public Service Commission (PSC).  This review did not find official Florida-specific measurements of data center tax payments, jobs, or water use, so this section is limited to law and regulatory status.

**Sales tax exemption.**  Section 212.08(5)(r), Florida Statutes, exempts "data center property" from state sales and use tax.  To qualify, the data center's owners and tenants must make a cumulative capital investment of $150 million or more, and the facility must have a critical IT load of 100 megawatts or higher, with at least 1 megawatt dedicated to each owner or tenant.  The facility must be constructed on or after 1 July 2017, and both requirements must be met within 5 years after construction begins.  Exempt property includes construction materials, machinery, equipment, servers, and software, and "also includes electricity used exclusively at a data center."  The Department of Revenue may not issue a temporary exemption certificate after 30 June 2037.  The 2026 law described below did not amend this exemption.  This review did not find an official published estimate of the exemption's annual cost.

**Chapter 2026-65, Laws of Florida (CS/CS/SB 484).**  The Legislature passed the bill on 13 March 2026.  It was approved on 7 May 2026, and most provisions took effect 1 July 2026.  The law:

- Defines a "large load customer" as one with an anticipated monthly peak load of 50 megawatts or more at a single location, and bars splitting a load into smaller connections to avoid that status.
- Requires public utility tariffs to "reasonably ensure that each large load customer bears its own full cost of service and that such cost is not shifted to the general body of ratepayers."  It states that the risk of nonpayment "may not be borne by the general body of ratepayers."
- Lets the PSC approve tools such as contributions in aid of construction, minimum demand charges, incremental generation charges, financial guarantees, minimum load factors, take-or-pay provisions, and minimum contract terms with early termination fees.
- Bars tariffs from preventing curtailment of a large load customer's service to protect grid stability or public safety, and bars utilities from knowingly serving a large load customer that is a foreign entity as the law defines it.
- Required each public utility to file a compliant tariff by 1 October 2026.  Under s. 366.02, "public utility" does not include electric cooperatives or municipal utilities.
- States that local governments keep their comprehensive planning and land development authority over large load customers, and that such a customer may not be treated as an electric substation under s. 163.3208.
- For a "large-scale data center" (50 megawatts or more), bars a water use permit if the use is harmful to the area's water resources or is prohibited by local zoning and the comprehensive plan.  It requires reclaimed water in place of some or all of the request when a suitable supply is available and feasible, requires applications for an average of 100,000 gallons a day or more to list all water sources and losses and include a conservation plan, and requires a hearing before any permit is approved.
- Removes the option to extend the 12-month confidentiality period for economic development records about data centers.
- Directs the Office of Program Policy Analysis and Government Accountability (OPPAGA) to contract for an independent study of data center impacts, including tax revenue, land and water use, energy costs and rates, and public health and safety, due 1 July 2027.

**Utility tariffs at the PSC.**  Florida Power & Light's (FPL) Large Load Contract Service tariffs, LLCS-1 and LLCS-2, were approved in FPL's 2025 rate case settlement, Order No. PSC-2026-0022-S-EI, issued 22 January 2026 in Docket No. 20250011-EI.  The tariff sheets apply to customers with projected new or incremental load of 50 MW or more and a projected load factor of 85 percent or more at a single location.  LLCS-1 is limited to zones near Sunbreak in St. Lucie County, Tesoro in Martin County, and Sugar in Palm Beach County, with a combined cap of 3 GW.  FPL testimony supporting the settlement described a 70 percent minimum take-or-pay demand charge, a twenty-year service agreement, and exit fees for early termination.  On 1 October 2026, FPL asked the PSC to find its existing LLCS tariffs compliant with s. 366.043 and proposed related revisions (Docket No. 20260149-EI).  PSC staff recommended suspending the proposed revisions to allow more review.  This page has not confirmed a final decision on that petition.

On 3 November 2026, the PSC voted to deny Duke Energy Florida's proposed large load tariffs (Docket No. 20260064-EI).  The Commission found that the tariffs "exclude certain large load customers who would otherwise qualify under the law's definition" and that Duke "had not provided sufficient evidence" that its existing rates and proposed protections would reasonably ensure each large load customer bears its full cost of service.  Duke must file new tariffs for review.  Tampa Electric (Docket No. 20260146-EI, filed 30 September 2026) and Florida Public Utilities (Docket No. 20260148-EI, filed 1 October 2026) also filed large-load tariff petitions.

What this shows: Florida law now states that large-load costs and nonpayment risk should not shift to other customers of investor-owned utilities.  Whether a given tariff meets that standard is decided docket by docket at the PSC, and several of those reviews were still open on 10 November 2026.

## Community benefit agreements

A community benefit agreement (CBA) is a signed contract between a developer and a local government, or sometimes community groups, that lists what the project will pay or do beyond ordinary taxes.  The terms vary widely, so the document itself matters more than any summary.  Two recent county examples show the range.

**Doña Ana County, New Mexico (Project Jupiter).**  The CBA was executed on 12 November 2025.  It was offered "as an inducement for the County to issue the three series of industrial revenue bonds in the par amount of up to $165,000,000,000," along with Local Economic Development Act support.  The project site is about 819 acres, and the companies committed to an initial capital investment of at least $50 billion within the first five years of the financing term.  Its payment schedule lists $4 million for local workforce development and education, $1.5 million toward a new Boys and Girls Club, $250,000 for a desalination study for drinking water, $150,000 for community college connectivity, $1 million for habitat restoration ($500,000 by the end of 2026, then $50,000 a year through 2036), and $4.5 million in county project funds paid from 2025 to 2028 as consideration for a building permit fee reduction.  The county's project page also lists annual payments to the county for 30 years.  The agreement limits enforcement: the county's "sole and exclusive remedy" for a company failure runs through the bond lease agreements, with no separate claim for damages, though unpaid scheduled payments can be sought from a guarantor.  The companies may terminate the CBA if they abandon the incentives on or before 31 December 2026.  The agreement said construction was expected to begin in the fourth quarter of 2025, pending permits and approvals, with initial capacity expected in the fourth quarter of 2026.  This page has not confirmed the project's current construction or operating status from an official source.

**Barber County, Kansas (Project Helium).**  The county's 31 August 2026 release lists $5.5 million in community benefit payments to cover county costs during construction, scheduled at $500,000 by the end of 2026, $3 million in 2027, and $1 million in each of 2028 and 2029.  Google is to inventory roads before and after construction, reimburse county engineering inspection costs, and provide $5 million in security for road work.  The county said the agreements also address setbacks, lighting, screening, stormwater, sound limits, generator operations, air quality compliance, water and wastewater testing, and decommissioning at the end of operations.

What to look for in any CBA: whether payments are fixed dollar amounts or depend on buildings coming online, who can enforce it and how, whether it ends if incentives are dropped, and whether water, sound, and job terms have numbers attached.

## Questions residents can ask at a hearing

These questions come straight from the gaps the sources above identify.  Ask for a named document and a date with each answer.  A longer list for local officials is in our [questions for local government brief](https://datacenterskilledtrades.com/briefs/local-gov-questions/).

1. Is this project proposed, approved, under construction, or operating?  Which approvals are still pending?
2. What property tax will the project pay at each phase, at the current tax rate, and is any abatement, exemption, or reduced computer-equipment rate part of the deal?
3. Which state or local incentives will the project use, and what is their estimated value over the life of the agreement?
4. How many workers will be on site at the construction peak, and how many full-time employees, not counting contractors, once it operates?  Is any job number a binding minimum?
5. What cooling system will it use, what is the estimated daily and peak water use, and where does the water come from?
6. Has the utility filed a load study?  What new substations or transmission lines are needed, and who pays for them?
7. Is there a large-load rate class or minimum-demand contract that protects other customers if the load never shows up or the site closes?
8. Has a sound study modeled noise at the nearest homes and schools, including low-frequency sound, and what limit will apply after it opens?
9. How often will backup generators run for testing, and what emissions standard do they meet?
10. Is there a community benefit agreement?  Are its payments fixed or conditional, and who can enforce it?
11. In Florida: which large-load tariff will apply, has the Public Service Commission approved it under s. 366.043, and will the project need a water use permit as a large-scale data center?

## Frequently asked questions

### Do data centers lower local property taxes for homeowners?

It depends on local tax rates and the size of the local data center market.  Loudoun County, Virginia, cut its real property tax rate from $0.865 to $0.805 per $100 of assessed value for calendar year 2025 and attributed the cut to rising real property values.  JLARC found data center revenue ranged from under 1 percent to 31 percent of total local revenue in five Virginia localities.  State and local tax breaks reduce what a locality collects.

### How many permanent jobs does a data center create?

Fewer than its construction phase.  JLARC reported industry estimates of about 50 full-time workers at a typical 250,000-square-foot data center, about half of them contractors, compared with about 1,500 workers on site at the construction peak.  Signed agreements for larger campuses sometimes set higher minimums, such as 750 full-time equivalent jobs for the planned Project Jupiter campus in New Mexico.

### Will a data center raise my electric bill?

It depends on how your utility and regulators allocate costs.  JLARC found Virginia data centers were paying their full cost of service, but estimated that growing demand could raise generation and transmission costs for a typical Dominion residential customer by $14 to $37 a month in real dollars by 2040.  Rate classes and minimum-demand contracts for large loads are tools regulators have used to address that risk, including in Virginia's 2025 Dominion review and in Florida's 2026 law.

### How much water does a data center use?

It ranges from less than a household to hundreds of millions of gallons a year, depending on size and cooling design.  JLARC found most Virginia data centers use about as much as an average large office building, 6.7 million gallons a year, or less, while one building used 243 million gallons in 2023.

### What did Florida's 2026 data center law do?

Chapter 2026-65, Laws of Florida, effective 1 July 2026, requires utility tariffs to reasonably ensure that customers of 50 megawatts or more bear their own full cost of service, keeps local planning and zoning authority, adds water permit requirements and a hearing for large-scale data centers, and orders an independent state study due 1 July 2027.  It did not change Florida's data center sales tax exemption.

## What this does and does not show

The JLARC report adds the trade-offs in one place: most economic benefit arrives during construction, operating staff are small, current Virginia rates were found to cover data centers' cost of service, and future system costs are likely to rise for all customers.  Incentives are a real public cost, as Virginia's $928.6 million in FY 2023 sales tax savings shows, and Illinois paused new incentive agreements in 2026 to study that question.  Community benefit agreements can add fixed payments and binding job, water, road, and sound terms, but their value depends on how they are written and enforced.  Florida's 2026 law sets a full-cost-of-service rule for large-load customers of investor-owned utilities, while the PSC's reviews of individual tariffs were still in progress on 10 November 2026.

The Loudoun record shows documented tax collections tied to computer equipment in data centers, a lower real property tax rate in calendar year 2025 than in 2024, and a county warning not to treat data center revenue as a stable base for recurring expenses.  It also shows nearly 200 operating data centers in the eastern county, a 55 dBA residential property-line standard, persistent tonal-noise complaints, and zoning work that is still underway.  National laboratory and EIA documents show large and rising electricity and water use at the U.S. scale, with 2030 and 2050 figures labeled as forecasts.  The Virginia SCC record shows a completed 2025 biennial review that raised Dominion base rates and created a 2027 large-load rate class with minimum-demand and contract terms.  None of those sources supplies a universal jobs multiplier, and this page does not invent one.

If a developer, utility, or local presentation claims that a specific project will create a stated number of jobs, a stated tax payment, or a stated water or power volume, ask for the named filing and the date, and ask whether the project is proposed, approved, under construction, or operating.

## How to cite this page

J. Rin, USAF Veteran.  "What a Local Data Center Means for Residents."  DataCenterSkilledTrades.com.  Published 10 November 2026.  Last reviewed 10 November 2026.  https://datacenterskilledtrades.com/guides/what-a-local-data-center-means-for-residents/

When quoting a single figure, cite the original source named in the [key numbers table](https://datacenterskilledtrades.com/guides/what-a-local-data-center-means-for-residents/#key-numbers) as well as this page.  Corrections and questions: [welcome@datacenterskilledtrades.com](mailto:welcome@datacenterskilledtrades.com).  Corrections are made in place, and the review date above is updated.

## Sources

Every link below returned HTTP 200 when retrieved on 10 November 2026.  Quotations and figures are taken from these documents, not from secondary summaries.

1. County of Loudoun, Virginia, *Popular Annual Financial Report, Fiscal Year Ended June 30, 2025*.  [loudoun.gov/DocumentCenter/View/218245](https://www.loudoun.gov/DocumentCenter/View/218245/FY-2025-Popular-Annual-Financial-Report)
2. Loudoun County, *Data Center Fact Sheet*, as of 1 March 2026.  [loudoun.gov/DocumentCenter/View/222193](https://www.loudoun.gov/DocumentCenter/View/222193/FINAL-Data-Center-Fact-Sheet-2026).  County hub: [loudoun.gov/datacenters](https://www.loudoun.gov/datacenters)
3. Loudoun County, "Data Centers: Noise and Air Quality Concerns."  [loudoun.gov/6405/Noise-Air-Quality-Concerns](https://www.loudoun.gov/6405/Noise-Air-Quality-Concerns)
4. Smith, S.J., Hubbard, A., Newkirk, A., Ganeshalingam, M., Holecek, B., Sartor, D., Mills, M., and Shehabi, A., *United States Data Center Energy Usage Report: 2025 Update*, Lawrence Berkeley National Laboratory, June 2026, LBNL-2001758.  [energy.gov document](https://www.energy.gov/documents/united-states-data-center-energy-usage-report-2025-update).  Bibliographic record: [OSTI 3374245](https://www.osti.gov/biblio/3374245)
5. Shehabi, A., Smith, S.J., Hubbard, A., and coauthors, *2024 United States Data Center Energy Usage Report*, Lawrence Berkeley National Laboratory, December 2024.  [eta-publications.lbl.gov PDF](https://eta-publications.lbl.gov/sites/default/files/2024-12/lbnl-2024-united-states-data-center-energy-usage-report_1.pdf)
6. U.S. Energy Information Administration, Courtney Sourmehi, "Data center server energy use grows across the commercial building stock," Today in Energy, 19 May 2026.  [eia.gov/todayinenergy/detail.php?id=67704](https://www.eia.gov/todayinenergy/detail.php?id=67704)
7. U.S. Energy Information Administration, Short-Term Energy Outlook, Electricity, Coal, and Renewables, release date 6 October 2026.  [eia.gov/outlooks/steo/report/elec_coal_renew.php](https://www.eia.gov/outlooks/steo/report/elec_coal_renew.php)
8. Virginia State Corporation Commission, "In Biennial Review Ruling, SCC Creates New Class for Large-Scale Energy Users," 25 November 2025, Case No. PUR-2025-00058.  [SCC news release](https://www.scc.virginia.gov/about-the-scc/newsreleases/release/scc-issues-order-on-dev-biennial-review-2025/scc-rules-in-dev-biennial-review-case.html)
9. Virginia State Corporation Commission, Final Order, Case No. PUR-2025-00058.  [SCC docket PDF](https://www.scc.virginia.gov/docketsearch/DOCS/89g601%21.PDF)
10. Virginia State Corporation Commission, "SCC Data Center Initiatives," posted 24 February 2026.  [SCC fact sheet PDF](https://www.scc.virginia.gov/media/sccvirginiagov-home/about-the-scc/fact-sheets/scc-data-center-initiatives-02-2026.pdf)
11. Code of Virginia section 15.2-2209.5, "Siting of data centers; site assessment" (2026, cc. 567, 568).  [law.lis.virginia.gov](https://law.lis.virginia.gov/vacode/title15.2/chapter22/section15.2-2209.5/)
12. U.S. Bureau of Labor Statistics, Current Employment Statistics, series [CES5051800001](https://data.bls.gov/timeseries/CES5051800001) (NAICS 518), [CES2000000001](https://data.bls.gov/timeseries/CES2000000001) (NAICS 23), and [CES2023800001](https://data.bls.gov/timeseries/CES2023800001) (NAICS 238), retrieved 10 November 2026.
13. Joint Legislative Audit and Review Commission, *Data Centers in Virginia*, Report 598, 9 December 2024.  [jlarc.virginia.gov report page](https://jlarc.virginia.gov/landing-2024-data-centers-in-virginia.asp).  Full report: [Rpt598.pdf](https://jlarc.virginia.gov/pdfs/reports/Rpt598.pdf)
14. Illinois Department of Commerce and Economic Opportunity, "Data Center Investment Tax Exemptions and Credits."  [dceo.illinois.gov](https://dceo.illinois.gov/expandrelocate/incentives/datacenters.html)
15. Office of the Governor of Illinois, news release on pausing new data center tax incentives, 5 June 2026.  [Governor's newsroom](https://gov-pritzker-newsroom.prezly.com/gov-pritzker-pauses-new-data-center-tax-incentives)
16. Doña Ana County, New Mexico, *Project Jupiter Community Benefits Agreement*, executed 12 November 2025.  [County-hosted PDF](https://cms2.revize.com/revize/donaanacounty/Documents/About%20Us/Economic%20Development%20Projects/Community%20Benefits%20Agreement%20(CBA)%20Executed.pdf).  County project page: [donaana.gov Project Jupiter commitments](https://www.donaana.gov/departments/administration/economic_development/project_jupiter/project_commitments.php)
17. Board of Barber County Commissioners, Kansas, "Barber County Commissioners Announce Agreement Terms for Project Helium Data Center Development," 31 August 2026.  [barber.ks.gov press release](https://barber.ks.gov/uploads/5/6/1/9/56198487/press_release.pdf)
18. Florida Statutes s. 212.08(5)(r), "Data center property," 2026 Florida Statutes.  [flsenate.gov/Laws/Statutes/2026/212.08](https://www.flsenate.gov/Laws/Statutes/2026/212.08)
19. Chapter 2026-65, Laws of Florida (CS/CS/SB 484), approved 7 May 2026.  [laws.flrules.org/2026/65](https://laws.flrules.org/2026/65).  Definition of "public utility": [s. 366.02](https://www.flsenate.gov/Laws/Statutes/2026/366.02)
20. Florida Public Service Commission, "FPSC Issues Decision on Duke Energy Florida's Large Load Tariff Petition," 3 November 2026.  [floridapsc.com news release](https://www.floridapsc.com/news-links/12359).  Vote sheet, Docket No. 20260064-EI: [Document No. 07689-2026](https://www.floridapsc.com/pscfiles/library/filings/2026/07689-2026/07689-2026.pdf)
21. Florida Public Service Commission staff recommendation, Docket No. 20260149-EI, 22 October 2026 (cites Order No. PSC-2026-0022-S-EI, 22 January 2026, Docket No. 20250011-EI).  [floridapsc.com recommendation](https://www.floridapsc.com/pscfiles/website-files/PDF/Agendas/archive/261103cc/26110311.html)
22. Florida Power & Light Company, LLCS-1 and LLCS-2 tariff sheets as filed 3 September 2026, Docket No. 20260001-EI, Document No. 06140-2026.  [floridapsc.com PDF](https://www.floridapsc.com/pscfiles/library/filings/2026/06140-2026/06140-2026.pdf).  Settlement testimony on LLCS terms: hearing transcript Volume 20, Docket No. 20250011-EI, [Document No. 14911-2025](https://www.psc.state.fl.us/library/FILINGS/2025/14911-2025/14911-2025.pdf)
23. Florida Public Service Commission, electric docket list (Docket Nos. 20260146-EI and 20260148-EI).  [floridapsc.com docket list](https://www.floridapsc.com/psc-docket-list?DocketType=D&IndustryCode=E)