# Texas power projects with signed ERCOT agreements

Canonical: https://datacenterskilledtrades.com/power/texas-grid-projects/

1. [Home](/)
2. [Power and Industrial Trades](/power/)
3. Texas grid projects

Power and industrial trades · Texas grid queue

# Texas power projects with signed ERCOT agreements

The October 2026 ERCOT interconnection report lists 1,736 Texas power projects totaling 445,897.64 MW.  577 of them already have a signed interconnection agreement, totaling 137,409.68 MW.  Those are the most advanced projects in the queue.  Here is where they sit, which trades they need, and how to get ready.

By the DataCenterSkilledTrades research desk.  Figures from the October 2026 ERCOT GIS Report.

Queue snapshot, October 2026 GIS Report

577 signed interconnection agreements, totaling 137,409.68 MW.  These are the most advanced projects in the ERCOT queue.

- The full report covers 1,736 Texas projects and 445,897.64 MW.
- A signed interconnection agreement is a contract to connect to the ERCOT grid.  Final construction still depends on financing, permits, and the developer's schedule.
- Solar leads the signed list at 63,132.63 MW across 249 projects, then batteries at 36,511.87 MW (212 projects), wind at 20,510.12 MW (83), and gas at 17,255.06 MW (33).
- 69 of these 577 projects also appear in the federal EIA-860M inventory for September 2026, matched by plant name and county.

The useful move now is to get training and credentials in order, then watch the job boards for verified openings.

## On this page

1. [Queue snapshot](#status)
2. [Signed capacity by fuel](#fuels)
3. [Counties and metros](#places)
4. [Trades and local pay](#trades)
5. [Registered apprenticeship sponsors](#apprenticeships)
6. [How to get ready](#prepare)
7. [Questions people ask](#faq)
8. [Sources](#sources)

## Signed capacity by fuel

These totals are the 577 projects with a signed interconnection agreement in the October 2026 GIS report.  Fuel types follow ERCOT's technology codes, aligned to EIA categories.

- Solar: 63,132.63 MW, 249 projects, 45.9% of signed capacity
- Batteries: 36,511.87 MW, 212 projects, 26.6% of signed capacity
- Wind: 20,510.12 MW, 83 projects, 14.9% of signed capacity
- Gas: 17,255.06 MW, 33 projects, 12.6% of signed capacity

The gas total includes 9 combined-cycle units (8,231.4 MW), 13 combustion turbines (7,406.17 MW), 10 internal-combustion engines (1,603.49 MW), and 1 steam turbine (14 MW).

## Counties and metros with the most signed capacity

A large share of signed capacity sits in rural West and North Texas.  The Northwestern Region of Texas nonmetropolitan area alone has 141 projects totaling 42,678.93 MW.  Among metropolitan areas, Houston leads, then Austin, Corpus Christi, San Antonio, Dallas-Fort Worth, and Abilene.

Top counties by signed-agreement capacity, ERCOT GIS Report October 2026:

| County | Area | Projects | Capacity (MW) |
| --- | --- | --- | --- |
| Brazoria County | Houston-Pasadena-The Woodlands | 25 | 5,674.4 |
| Wharton County | Coastal Plains nonmetro | 21 | 5,160.19 |
| Pecos County | Northwestern nonmetro | 20 | 5,048.26 |
| Borden County | Northwestern nonmetro | 9 | 3,736.75 |
| Bastrop County | Austin-Round Rock-San Marcos | 8 | 3,637.37 |
| Wilbarger County | Northwestern nonmetro | 8 | 3,520.9 |
| Lamar County | North Region nonmetro | 15 | 3,502.29 |
| Deaf Smith County | Northwestern nonmetro | 5 | 3,118.81 |
| San Patricio County | Corpus Christi | 11 | 2,549.49 |
| Milam County | Hill Country nonmetro | 15 | 2,509.61 |

Top metros by signed-agreement capacity, ERCOT GIS Report October 2026:

| Metro | Projects | Counties | Capacity (MW) |
| --- | --- | --- | --- |
| Houston-Pasadena-The Woodlands | 48 | 8 | 11,839.56 |
| Austin-Round Rock-San Marcos | 13 | 3 | 4,976.89 |
| Corpus Christi | 17 | 2 | 3,796.72 |
| San Antonio-New Braunfels | 18 | 5 | 3,346.57 |
| Dallas-Fort Worth-Arlington | 18 | 7 | 3,257.2 |
| Abilene | 14 | 3 | 2,907.38 |

In the Houston metro, Brazoria County accounts for 5,674.4 MW of the 11,839.56 MW total.  In the Austin metro, Bastrop County accounts for 3,637.37 MW of the 4,976.89 MW total.

## Trades these builds need, and what they pay

We map trades to each project by its generation technology, then join official BLS OEWS May 2025 wages for Texas and for each metro.  Electricians, lineworkers, and instrumentation technicians are mapped to all 577 signed projects.  Ironworkers are mapped to 567.  Millwrights and welders are mapped to the 116 wind and gas projects.  Plumbers and pipefitters are mapped to the 33 gas projects, which total 17,255.06 MW.

- Electricians: plant wiring, collection systems, and switchgear on solar, battery, wind, and gas sites.  The Texas median for electricians (SOC 47-2111, all industries) is $58,570, or $28.16 an hour, with 76,770 employed in the state.
- Lineworkers: interconnection, collector lines, and switchyard work on every fuel type in this list.  The Texas median for electrical power-line installers and repairers (SOC 49-9051) is $78,940, or $37.95 an hour, with 17,280 employed in the state.
- Pipefitters: fuel-gas piping, and steam piping on combined-cycle and steam units.  The Texas median for plumbers, pipefitters, and steamfitters (SOC 47-2152) is $59,840, or $28.77 an hour, with 44,090 employed in the state.
- Millwrights and welders: turbine, engine, and nacelle mechanical set, plus process and structural welding, on the wind and gas projects.  Texas medians are $62,630 for millwrights (SOC 49-9044) and $53,340 for welders (SOC 51-4121).

BLS OEWS May 2025 median annual pay, all industries, in the top signed-capacity metros:

| Area | Electrician | Pipefitter | Lineworker |
| --- | --- | --- | --- |
| Texas (statewide) | $58,570 | $59,840 | $78,940 |
| Houston-Pasadena-The Woodlands | $59,180 | $61,300 | $82,710 |
| Austin-Round Rock-San Marcos | $60,390 | $62,810 | $82,120 |
| Dallas-Fort Worth-Arlington | $59,010 | $61,250 | $77,910 |
| San Antonio-New Braunfels | $57,010 | $58,180 | $78,030 |
| Corpus Christi | $59,410 | $59,390 | $77,770 |
| Abilene | $47,400 | $51,790 | $79,600 |

These are all-employer medians, not a quote for a specific plant.  Construction work can add overtime or per diem when a contractor offers it.  Instrumentation technicians (SOC 17-3023) have a Texas median of $74,050.  Ironworkers (SOC 47-2221) have a Texas median of $52,240.

## Registered apprenticeship sponsors in the top metros

These names come from the U.S. Department of Labor Office of Apprenticeship partner-sponsors file dated November 11, 2026.  We list joint apprenticeship programs and contractor-association schools for electricians and pipefitters in the leading metros.  Cities only, no contact details.  Confirm current openings with the sponsor.

Houston-Pasadena-The Woodlands:

- Houston Electrical JATC, Houston
- IEC Texas Gulf Coast Chapter, Houston
- Industrial Electrical Training School, Houston
- 5K Electrical Apprenticeship Program, Houston
- Galveston Electrical JATC, Texas City
- Houston Pipefitters JATC, Deer Park
- Houston Area Plumbing JAC, Houston

Dallas-Fort Worth-Arlington:

- East Texas Electrical JATC, Arlington
- IEC Fort Worth, Fort Worth
- North Texas Electrical JATC, Grand Prairie
- IEC Dallas, Irving
- Fort Worth Pipe Trades Training Center Trust (JATC), Fort Worth
- United Assoc. Dallas #100 Plumbers & Pipefitters, Garland

Austin-Round Rock-San Marcos:

- Austin Electrical JATC, Austin
- CenTex IEC, Austin
- Austin Area Plumbers & Pipefitters JATC, Austin

San Antonio-New Braunfels:

- San Antonio Chapter IEC, San Antonio
- South Texas Electrical JATC, San Antonio
- SA Area Plumbers & Pipe Fitters JATC, San Antonio

Corpus Christi:

- Texas Gulf Coast Electrical JATC, Corpus Christi

The same Labor Department file lists additional contractor sponsors in these metros.  For a wider Texas directory of registered programs, see [RegisteredTradeSchools](https://registeredtradeschools.com/).

## How to get ready

A signed grid agreement shows you where projects are furthest along.  Use that map to choose a trade, a training path, and a region, then watch for verified openings.

- Learn the role: read the [electrician](/roles/data-center-electrician-salary/), [pipefitter](/roles/liquid-cooling-pipefitter/), and [HVAC technician](/roles/critical-facilities-hvac-technician/) pages for pay, skills, and credentials those crafts already use.
- Talk to a sponsor: the joint apprenticeship programs above are a direct path into electrical and pipe work in the metros with the most signed urban capacity.
- Watch verified jobs: check the [job board](/jobs/) and the [Dallas-Fort Worth](/jobs/dallas-fort-worth/) board for current, verified postings.  We list a job only when a posting is still open.
- Know the Texas markets: the [North and Central Texas](/markets/north-and-central-texas/) and [West Texas](/markets/west-texas/) market pages cover local pay, unions, and training already checked for those regions.

For plants and lines that already have financing or a construction start on the public record, use the [Texas plant and grid jobs](/power/texas-power-plant-grid-jobs/) guide.  That page and this one answer different questions: funded and approved work there, the signed interconnection queue here.

## Questions people ask

### What does a signed ERCOT interconnection agreement mean?

It is a contract to connect a project to the ERCOT grid.  In the October 2026 GIS report, 577 of 1,736 Texas projects have that signature, totaling 137,409.68 MW.  Those are the most advanced projects in the queue.  Final construction still depends on financing, permits, and the developer's schedule.

### Which fuel types have the most signed capacity?

Solar leads the signed list at 63,132.63 MW across 249 projects.  Batteries follow at 36,511.87 MW (212 projects), then wind at 20,510.12 MW (83) and gas at 17,255.06 MW (33).

### Where is most of this signed capacity located?

The largest single county is Brazoria County, with 25 projects and 5,674.4 MW, in the Houston-Pasadena-The Woodlands metro.  Most signed capacity sits in nonmetropolitan regions, led by the Northwestern Region of Texas at 42,678.93 MW across 141 projects.  Among metros, Houston leads at 11,839.56 MW, then Austin, Corpus Christi, San Antonio, Dallas-Fort Worth, and Abilene.

### How can I get ready for this work?

Start with the electrician, pipefitter, and HVAC role pages on this site, then talk with a registered apprenticeship sponsor in a nearby metro.  Use the job boards for verified openings.  A signed grid agreement tells you where projects are furthest along.  It is not, by itself, a job opening at a named site.

## Sources

One official source per fact cluster.  Wage and sponsor figures are joined from those official files to the projects in this report.

1. Project counts, megawatts, fuels, counties, and signed interconnection agreements: [ERCOT Generator Interconnection Status (GIS) Report, October 2026](https://www.ercot.com/mp/data-products/data-product-details?id=PG7-200-ER) (report run November 1, 2026).
2. Federal plant inventory overlap, matched by name and county: [EIA Preliminary Monthly Electric Generator Inventory (Form EIA-860M), September 2026](https://www.eia.gov/electricity/data/eia860m/) (released October 23, 2026).
3. Occupation medians for Texas and the metros above: U.S. Bureau of Labor Statistics, Occupational Employment and Wage Statistics, May 2025.
4. Registered apprenticeship sponsor names and cities: [U.S. Department of Labor Office of Apprenticeship partner-sponsors file](https://www.apprenticeship.gov/), dated November 11, 2026.

## Next steps

Pick a trade page, then use a Texas job board or the funded-plant guide, depending on whether you want current openings or projects already on the public financing record.

- [Electrician pay and path](/roles/data-center-electrician-salary/)
- [Verified job boards](/jobs/)
- [Funded Texas plant jobs](/power/texas-power-plant-grid-jobs/)