Price the delay
Delay is a number. Take your contracted or expected rent, multiply by megawatts, multiply by months. At an assumed $140 per kW-month, a 100 MW phase costs $14 million for every month it sits dark. Eighteen months of queue slippage is a quarter of a billion dollars of deferred revenue before you count carrying costs on the land, equipment, and staff.
That number sets your budget for bridge power. If on-site generation costs more per kWh than the grid but gets you energized 24 months sooner, the premium is usually the cheap part of the deal.
What goes wrong in the queue
Utilities are short on transmission, substation capacity, equipment, and often generation, all at once. Studies run in sequence, and a withdrawal ahead of you can force a restudy that moves your date. Tariffs for large loads are tightening with minimum demand charges, long contract terms, and collateral requirements. Build your schedule from the most conservative date the utility will put in writing, and treat anything earlier as upside.
The on-site options
| Option | Lead time pressure | Strengths | Constraints |
|---|---|---|---|
| Reciprocating gas engines | Shorter than turbines, often 12 to 24 months | Modular, good part-load efficiency, fast ramp | Many units, large footprint, emissions per MW, maintenance labor |
| Aeroderivative turbines | Several years for new slots | Compact, fast start | Slot availability, fuel pressure, efficiency at part load |
| Industrial and combined-cycle turbines | Major OEMs report backlogs toward the end of the decade | Best efficiency at scale | Slot reservation required years ahead, large capital, long permitting |
| Fuel cells | Moderate | Low local emissions, quick deployment | High cost per kW, gas supply, vendor capacity |
| Battery storage | Moderate | Smooths load swings, provides ride-through | Duration limits, cost |
Most real projects mix these. Engines or aeroderivatives bring the first phase online. Storage handles the load swings. A larger unit follows if the site is meant to stay islanded.
Gas supply is the constraint nobody budgets early
One gigawatt of generation burns on the order of 160 to 230 million cubic feet of gas per day, depending on whether you run combined cycle or simple cycle. That is a pipeline lateral, firm transportation capacity, and a meter station, none of which show up on a generator quote.
Questions to answer before site control closes:
- Where is the nearest pipeline with spare capacity, and who owns it?
- Is service firm or interruptible? Interruptible gas under a campus that cannot go down is a contradiction.
- What pressure does the turbine or engine need, and does the lateral require compression?
- How long does the lateral take to permit and build? Eighteen to thirty-six months is common.
If the answers are bad, the generation option is dead, whatever the turbine OEM says.
Permits and neighbors
Large combustion sources trigger air permitting that commonly runs 12 to 24 months, with emissions controls such as selective catalytic reduction on the larger units. Developers who stood up temporary turbines without clean permit paths have drawn regulatory action and community opposition, and schedule recovery after a stop order is slow. Put an air permit consultant and a community relations lead on the team before you order equipment.
Designing an island that holds
A campus on its own generation has no grid to lean on. Design for it.
- Redundancy. Plan N+2 on generation, or keep a grid connection as the second source. Equivalent-to-2N is expensive on prime power.
- Load swings. AI training workloads can change power draw by tens of megawatts in moments. Generators need storage or fast-response equipment in front of them to ride that out, and the OEM must confirm step-load and ramp behavior in writing.
- Black start and islanding controls. Specify them, test them, and put them under the same commissioning discipline as the UPS.
- Exit design. Size the switchyard, MV distribution, and main buses for the final grid-connected state. When the utility finally energizes you, the on-site plant becomes backup or peaking capacity. Decide at the outset whether it stays, moves, or sells.
Existing nuclear
Contracts with operating plants, restarts of recently shuttered units, and uprates are the nuclear power that can show up inside a data center development window. Announced restart targets sit around 2027 to 2028 for a handful of units. Supply is thin, and deals are few.
Co-locating load directly at an operating plant has run into regulatory friction, including FERC's handling of an interconnection arrangement at a Pennsylvania plant in late 2024. Treat co-location structures as subject to change, and get counsel's read on the current rules and pending dockets before you sign.
SMR power purchase agreements
Several large buyers have signed development agreements with small modular reactor companies. Read them for what they are: options on future power from first-of-a-kind plants. The credible dates for first commercial units in North America cluster around 2030 to 2035. Fuel supply, especially HALEU for some designs, and NRC licensing remain open risks.
Protect the program with structure:
- Keep SMR off the critical path of phase one. If opening-day power depends on a reactor that has not broken ground, you have no schedule.
- Stage the commitment. Pay for milestones: construction permit, fuel contract, first concrete, fuel load. Avoid large upfront capital against a design that has not been licensed.
- Define COD remedies. Require delay damages or replacement power obligations when the reactor misses its date, and credit support from a parent that can pay them.
- Keep the exit open. Termination rights tied to licensing failure, cost escalation above an agreed cap, or fuel supply loss.
- Size for a later phase. Treat nuclear as the second or third block of a campus, supplied after the gas and grid power already running.
Sequence by time horizon
| Horizon | Power source | Role |
|---|---|---|
| 0 to 3 years | Engines, aeroderivatives, storage, fuel cells | Bridge and first-phase prime power |
| 3 to 7 years | Utility interconnection, long-term PPAs, restarted nuclear | Primary supply, on-site plant steps back to backup |
| 7+ years | SMRs, advanced reactors | Long-term baseload for later phases |
Capital gates should tie to these horizons. Do not release spend on a phase until its power source holds a signed agreement, a permit path, and a delivery date you believe.